What is the standard timeline for a HDB renovation project?

• RCS Team — min read
Contact Us via WhatsApp
RCS Team — HDB Registered & BCA Approved Renovation Contractor Singapore
Written & Reviewed by Renovation Specialists · HDB Registered · BCA Approved · Since 2017
The RCS Team is a collective of licensed renovation professionals, project managers, interior designers, and on-site supervisors who have collectively delivered hundreds of HDB, condominium, and landed property renovation projects across Singapore since 2017. Our articles are written based on real on-site project experience — including hacking, wet works, carpentry, electrical rewiring, tiling, plumbing, and HDB permit submissions — and are cross-checked against official HDB and BCA guidelines. RCS holds HDB Registered Renovation Contractor status, BCA approval, bizSAFE Level 3, and active PMI membership.
✓ HDB Registered ✓ BCA Approved ✓ bizSAFE Level 3 ✓ PMI Member ✓ Since 2017
Editorial Standard: This article is authored by the RCS in-house renovation team based on first-hand project experience, cross-checked against publicly available HDB and BCA guidelines. Editorial & SEO Visibility by Redo · SingRank . Last reviewed: 23 August 2024.

Disclaimer: This article is published by the RCS Team for general informational purposes only and does not constitute professional advice.

A standard timeline for a HDB renovation will depend on the work needed. 

For example, let’s take a simple BTO kitchen cabinet package

After confirmation with your chosen renovation firm, you’ll need to choose the materials like laminate and quartz. 


Depending on whether you already have something in mind or just going to think about it, this can take anywhere from: 


Choosing of materials for kitchen cabinet

  • 3 days to up to 2 weeks for fickle minded homeowners


While going through this process, homeowners can already send their chosen laminate designs to renovation firm for them to start the drawing. Some renovation firm provides the 3D rendering. You’ll need to confirm with yours about it. 


The 3D rendering can take another: 


3D rendering

  • 3 days to 1 week. 

If you need to change the laminate designs, this can take up more time deciding on the final design to be used for your kitchen cabinet. While the process is taking place, the base of the kitchen cabinet can already be constructed and electrical points extended. 


For this to happen, decision on the layout of your kitchen cabinet would have been made. 


Base construction takes only: 

  • 1 day

Electrical works should also take only 

  • 1 day

After this it’s the taking of measurements for your kitchen cabinet. Once measurements, finalizing the layout and choosing laminate designs are done, fabrication can take:

  • 2 to 3 weeks

When fabrication is completed, delivery and installation can take another: 

  • 1 to 2 days

Followed by countertop measurement to installation another: 

  • 3 to 5 days

And finally its the installation of your electrical connections, switches and installation of your sink and tap. Considering that there is no glass backing for your kitchen cabinet. If there is the whole process will take longer. 


For renovation works that requires other trades as well like hacking, masonry, plastering, rewiring and more. Please check with us again for the complete breakdown of the works and timeline. 

We are committed to the success of your home renovation.  