The renovation is finished and the keys are back in your hand. Then the defects show up: a tile that rocks underfoot, a cabinet door that will not close, paint lifting near the window, a damp patch below the sink. You message the contractor, and the replies get slower, or stop.
If your own contractor will not fix renovation defects after handover, put every defect in one dated list with photos and send it to the contractor in writing. If nothing happens, you can file a claim at the Small Claims Tribunals (SCT). The tribunal lists a renovation contract among the claims it hears, and it can make a work order that requires a party to put a defect right, not only order a payment.
When a Contractor Refuses to Rectify Defects: What You Can Ask For
First, check which problem you have. If the defects are in a new HDB flat and came from HDB's own building work, they go through HDB's own process; our HDB BTO defects check and inspection checklist covers that route. If the defects are in work your own contractor did under your renovation contract, it is a dispute between you and the contractor. That is what this guide covers.
For that dispute, the page to read first is the SCT's page on small claim outcomes. It describes two kinds of order, and the difference matters when the problem is bad workmanship rather than a bill:
- Money order: one side pays the other a stated sum by a set date.
- Work order: "one party must rectify a defect in goods or damage to property, or make good any deficiency (lack or shortage) in the performance of services." The page adds that the order can spell out how the work is to be done.
That second order is easy to miss. A renovation work order in Singapore's small claims process tells the other side to come back and put the work right, which may be what you wanted from the start. Whether your case ends with a work order, a money order or neither is the tribunal's decision, not yours or the contractor's.
Steps 1 to 3: One Defect List, Dated Photos, One Written Notice

Do this before you escalate anything. The SCT's checklist before going to the tribunal expects you to walk through each invoice behind your claim and, in a renovation case, each defect you raise. The work you do now is the work the tribunal will ask for later.
- Make one defect list. Give each defect its own line: where it is, what is wrong, when you first noticed it. "Kitchen, third base cabinet from the left, door does not close" is useful. "Carpentry has problems" is not. Match each line to its item in your quotation; our guide on how to read a renovation quotation helps with that.
- Photograph every defect and keep your paperwork. Take the photos before anyone touches the defect. The SCT's filing page gives examples of supporting documents, and photographs, contracts, invoices, receipts, emails and messages are all on that list.
- Send one written notice. Send the full list in one email or chat message, photos attached. Ask the contractor for a date to come back and fix each item, and keep a copy. A phone call leaves no record; an email or a chat message is exactly the kind of document the filing page lists.

Our view: send the whole list at once, not one complaint a week. One complete, dated notice is easier for the contractor to act on, and easier for you to explain later. It also makes the timeline obvious if the contractor goes quiet.
A sample written notice you can adapt
Keep it short and factual. Number the defects so the photos and any later reply can refer to them. This is a sample to adapt, not a legal form:
Subject: Defects at [your address] after handover on [date]
Hi [contractor's name], after handover on [date] we found the defects below. Photos are attached, numbered to match.
1. Kitchen, third base cabinet from the left: door does not close. First noticed [date].
2. Common bathroom: floor tile beside the drain is loose. First noticed [date].
3. Living room: paint peeling above the window. First noticed [date].Please reply by [date] with when you can come back to fix each item. Thank you, [your name]
If the contractor replies, file the reply with your list. If they fix some items and not others, update the list so it shows what is still open and when you last asked. A list that shows what was fixed, what was not and when you chased it is far easier to explain than a long chat thread.
Can You Take a Renovation Contractor to the Small Claims Tribunals?
The SCT's eligibility page lists claims under a contract to provide services, and the example it gives is a "Renovation contract". Before you treat it as a Small Claims Tribunals renovation case, check the three limits on that same page:
- Claim value: up to $20,000, or up to $30,000 where both parties have given a Memorandum of Consent.
- Time limit: "All SCT claims must be filed within 2 years of the event which creates your cause of action." The filing page shows how the count works: for a contract broken on 15 November 2020, your last filing day was 15 November 2022.
- Outside its reach: a claim with a total value above $30,000, and a claim against a respondent based outside Singapore.
Filing is online. The filing page says every application is made in CJTS, the Community Justice and Tribunals System. You need a pre-filing assessment ID from CJTS to start. The documents you need are in the checklist below.
Once the claim is filed, the same page gives you 7 days to serve it, together with the Notice of Consultation, on the contractor. If you cannot serve it, you still go to the consultation; the registrar there may tell you to serve another way, such as by email.
Your checklist before you file
- The defect list, one line per defect, with the date you first noticed each one.
- Dated photos of every defect, taken before any repair.
- Your contract or signed quotation, invoices and receipts.
- Your written notice and every reply from the contractor.
- The date of the event your claim is about, checked against the 2-year filing limit.
- If the contractor is a business, its ACRA business profile, taken no more than 1 month before you file.
What It Costs and How Long It Takes
The filing fee depends on the claim amount and on who is filing. These are the figures on the SCT's filing page:
| Claim amount | Individual | Other entity (incl. sole proprietorships) |
|---|---|---|
| Up to $5,000 | $10 | $50 |
| Over $5,000 and up to $10,000 | $20 | $100 |
| Over $10,000 and up to $30,000 | 1% of the amount claimed | 3% of the amount claimed |
Three more points from the tribunal's pages:
- Going to a consultation or a hearing costs nothing extra. The SCT's checklist page says there are no charges for either.
- Most SCT cases end within 4 months of filing, according to the filing page.
- "Lawyers are not allowed to represent parties in proceedings before the SCT," the same filing page says. You present your own case, which is why the defect list matters.
What Happens After You File: Online Settlement, Consultation, Hearing
Filing does not send you straight to a hearing. The dispute can end at any of three stages, and the same defect list serves you at each one.
Online settlement. After a case is filed in CJTS, the judiciary's eNegotiation and eMediation page sets out two ways to settle without a court session. Only the respondent, which here is the contractor, can start eNegotiation, and it runs for up to 5 rounds of negotiation online. eMediation brings in a mediator appointed by the court; either side can apply, but the court has to approve it.
If either route ends in agreement, you do not need to go to court. If it does not, both sides attend the next court session already scheduled.
Consultation. According to the SCT's checklist page, every SCT claim starts with a consultation, where a registrar tries to resolve the dispute. You and the contractor both have to attend every consultation and hearing, and a party who stays away can have a default order made against them.
Hearing. If the consultation does not settle it, the same checklist page says the claim can go on to a hearing in front of a tribunal magistrate. Bring the same defect list, so you can explain each item.
If the Contractor Ignores the Order
An SCT order is final and binding on both sides, the outcomes page says. Winning, though, is not the same as getting the work done. If the contractor does not comply, the next step, execution or enforcement proceedings, is yours to start: "The SCT cannot execute or enforce the order on your behalf."
A work order has its own fallback. The outcomes page says the SCT can change a work order, or order the party who did not comply with it to pay money to the other side. So keep a record of what was ordered, the dates, and whether the contractor turned up.
What This Route Does Not Cover
- Water damage from the flat above or next door. The SCT's eligibility page puts property damage caused by a neighbour on its list of claims you cannot file there. For leaks between floors, see HDB ceiling leak between floors: who pays and which pipe is yours if it leaks.
- Bigger claims or overseas contractors. The SCT cannot hear a claim above $30,000 or one against a respondent outside Singapore.
HDB Rules Still Apply to Any Follow-Up Work
Whoever does any further work in your flat, HDB's rules still apply to you. HDB's page of important information on renovations makes you, the owner, responsible for the renovation in your flat, including making sure your contractor's work follows HDB guidelines. Under the Housing & Development (Renovation Control) Rules 2006, the same page adds, you may only use contractors listed in HDB's Directory of Renovation Contractors.
RCS is a renovation contractor too, so check us the same way you would check anyone else. Our guide shows how to check an HDB licensed contractor.
If you are planning more renovation work and want to talk it through with our team, our contact page has an enquiry form and WhatsApp.
Renovation Defects After Handover: Common Questions
Do I need a lawyer to claim against my renovation contractor at the SCT?
No. The SCT's filing page says lawyers cannot act for either side in SCT proceedings. You explain the case yourself at the consultation and, if it goes that far, at the hearing. A clear defect list with dated photos is what lets you do that.
How long do I have to file a claim for renovation defects?
The SCT's eligibility page sets a 2-year limit, counted from the event that gives rise to your cause of action, and it lists a claim filed later than that as one you cannot bring. The page does not say which event that is in your case, so keep your defect list and messages dated; they show what happened when.
This article is general information, not legal advice. It sets out what the Small Claims Tribunals and HDB publish on their own pages and does not predict the outcome of any claim. Check the linked judiciary.gov.sg pages for the current rules before you file. Last reviewed: 17 November 2026.